April 2018
Vision for STO Trail FAQ
March 3, 2018Grand Opening Ribbon Cutting Ceremony
May 16, 2017City Council Study Session
April 4, 2017
City Council Study Session (PDF)
January 10, 2017
City Council Minutes (PDF)
January 10, 2017Construction Award
November 2016Advertise for Construction Bids
August 23, 2016
The City Council rejected the bids received from the August 16, 2016 bid opening, due to irregularities in the bids, and authorized staff to rebid the project. The City anticipates rebidding the Sound to Olympics Trail project in the near future.
August 16, 2016
Bid Opening
April 12, 2016
STO Trail Phase 3 Grant Opportunity
August 2015
The 90% construction drawings are under review with WSDOT.
April 2015
The 50% construction drawings are under review with WSDOT.
November 18, 2014
November 18, 2014 City Council Study Session (PDF)
November 13, 2014November 13, 2014 Public Meeting
The Non-motorized Transportation Advisory Committee (NMTAC) has unanimously approved a Preferred Option for the Trail, on the east-side of the highway from Winslow Way to High School Road. A public meeting was held on Thursday, November 13th to discuss progress to date
October 29, 2014
October 29, 2014 Public Meeting
October 19, 2014
October 19, 2014 Site Walk
September 17, 2014
September 17, 2014 Public Meeting
August 4, 2014
Design Award
March 13, 2014
Request for Qualifications - Design Services (PDF)
2013Puget Sound Regional Council Award Letter (PDF)
2013Federal Grant (PDF)