Project Overview
The Annual Drainage program works to improve drainage conditions on the Island through small drainage improvement projects including, but not limited to, culvert repairs and replacement of aging storm drain lines that carry storm runoff from one side of the road to the other.
Update:
The 2023 Annual Drainage project consists of repairing a 48-inch crushed corrugated metal culvert pipe that runs along the east shoulder of Weaver Road in front of 341 Weaver Rd NW, Bainbridge Island, WA 98110. The work is anticipated to begin late July and will continue until early August. Residents should expect partial intermittent lane closures and up to 5 minute delays.
All dates are estimates and weather dependent.
Please see link below for project locations: