Timeline:
The Parking Strategy timeline runs from Summer 2017 through early 2018. The following schedule identifies some key dates in the project:
- Parking System Inventory - July 2017
- Data Collection - August and September 2017
- Survey and Survey Summary - August and September 2017
- Stakeholder Outreach - August 2017
- Task Force Meetings - Ongoing
- Public Open House - Late Fall 2017
- Project Report - Winter 201July 2018
- Public Outreach for proposed parking changes - Spring 2018