September 7 - The building exterior is ready for concrete footings to be poured to support the new stairwell addition. The interior floor slab is being prepared for the installation of new plumbing, and the exterior front wall will be prepped for the concrete footings to be poured to support the overall structural enhancements of the building frame.
July 29, 2022 - Construction continues on the City’s new Police and Court Facility, with the current focus on increasing the structural stability of the building to meet current codes for earthquake protection. The north wall has been removed for structural reinforcement, and the building foundation is being altered to improve “hold-downs” for the building’s structural systems.
July 7, 2022 - Demolition of interior walls on both floors started last week, with certain materials being sorted for potential re-use or donation.
June 3, 2022 - The community celebrated the groundbreaking of the new Police-Court facility. The new facility will be seismically sound, provide safety and privacy for victims and witnesses via interview rooms, offer increased storage space for evidence, accessibility by public transit, and add space for jury trials, among other improvements.
April 12, 2022 - City Council approved the construction contract with Clark Construction LLC in the amount of $7,570,449.