DESCRIPTION:

In coordination with the KPUD, the City will share costs associated with repaving the full road width following water main replacement by KPUD on Beach Crest Drive.  The paving of Beachcrest Drive will occur in the later part of August 2018.

  • Estimated start date:  June 2018
  • Estimated Completion:  August/September 2018

ACTIVITY:

  • Design & Permitting
  • Construction to be coordinated with the Roads Program contract.
  • 9/7/18 UPDATE:  Following resolution of the Local 302 Union Strike, the City’s contractor plans to return to work on Beachcrest Drive next week.
    9/14/18 - Paving Completed.