MILLER ROAD (CORE 40) SHOULDER IMPROVEMENTS

DESCRIPTION    
This project includes installation of six-foot (5-ft paved) shoulder improvements on Miller Road from Tolo to Peterson Hill.  It's included in the City's Core 40 Program envisioned to complete 40-miles of shoulder facilities on the Island. 

CURRENT ACTIVITY
Design and permits are 90% complete.

PREVIOUS ACTIVITY
10/25/16 - City Council approved design award.
2/16/16 - Resolution 2016-07 accepting a Federal Highway Transportation Grant.


SCHEDULE
It’s estimated the design to be complete in February/March with an anticipated construction advertisement in March/April.
-------------------------------------------------------------------------------------------------------------------

Select “NOTIFY ME” to subscribe to project notifications.


PRINT SCREEN


TITLE VI NOTICE:  The City of Bainbridge Island fully complies with Title VI of the Civil Rights Acts of 1964 and related statues in all programs and activities.  Those requiring disability accommodations and/or materials made available in alternate formats, please contact the City Clerk at 206.842.2545 or cityclerk@bainbridgewa.gov


Contact Us

  1. Chris Munter


    Project Manager
    Email

    Ph: 206-842-2016

    Staff Directory